 A county building inspector will conduct one or more inspections of a project during construction.
When all phases of construction are approved and
all agencies (i.e. Fire, Health, Planning) have given their final
approval, the Building Inspection Department will "final" the permit.
I'd Like to Know...
1. Foundation
Following rough grading and placement of concrete forms, reinforcing
steel, and all structural hardware, but prior to pouring concrete.
Property line must be established by a licensed surveyor so setbacks can
be verified.
2. Under Floor Framing - Raised Floor
When all girders, joist, plumbing, mechanical components have been
installed.
3. Floor
Insulation & under floor to be inspected prior to installing
sub-floor, plywood.
4. Roof Sheathing & Shear Inspection
When all nailing and shear transfers have been completed.
5. Framing Inspection
The building must be weather protected (windows, doors must be
installed) when all rough electrical, plumbing & mechanical systems have
been installed. Fire sprinklers are inspected by the Fire Dept.
6. Insulation Inspection
When all of the above items have been approved and before wall
coverings are installed.
7. Sheetrock/Exterior Lath
After all sheet rock has been installed, exterior lath and all corner
aid and weep screed have been installed.
8. Scratch Coat
After sheet rock has been installed and the scratch coat has cured for
48 hours minimum.
9. Shower/Tub Lath
10. Final
To be scheduled when the structure is ready for occupancy.
Note: Other departments/agencies must give their final approval before the building
inspector can "final" the structure. Examples of
these agencies include the Planning Department, Health Department,
Fire Department.
Further information may be obtained by speaking with a Permits
Center representative or by contacting a Building Inspector at (831)
755-5027
|