Public Works & Facilities
1441 Schilling Place
Salinas, CA 93901
(831) 755-5027
Fax
(831) 757-9516



Disclaimer:
Although every effort is made to provide complete and accurate information on this website and all its documents, users are advised to contact applicable County Resource Management Agency staff before making project decisions and fee estimates.

Palo Colorado Road Repair Projects

Print

Monterey County RMA is currently managing two projects on this road; (1) The Palo Colorado Emergency Repairs at Rocky Creek (Milepost 3.0 to 3.5) and Palo Colorado Storm Repairs from "the Hoist" to "Botcher's Gap" (Milepost 4.0 to 7.5). Here is a brief summary on both:

 

Palo Colorado Road Repair Update (Updated 8/31/17)

Repairs at Rocky Creek (Milepost 3.0 to 3.5)

The County is preparing plans to replace the existing damaged culverts underneath Palo Colorado Road and the Rocky Creek and Brandon Creek Crossings. The road has been temporarily resurfaced with aggregate base material and a temporary bridge has been placed near the Rocky Creek culvert crossing. Plans for permanent repairs are complete and County has applied for the necessary regulatory permits required to complete this work.  However, federal permits will not be issued in time to begin construction before this rain season (October 2017-April 2018).  Meanwhile, the County is proceeding with bidding so that we have a contractor ready and so we can prepare as much as possible ahead of beginning construction in Spring 2018.

If we get heavy rains this year resulting in high water flows within Rocky Creek, the County may need to pull the bridge temporarily to avoid damaging the bridge.  The County will monitor conditions throughout the winter and provide advanced notice of any action to pull the bridge.

Below is a brief outline of milestone dates for this project:

  • August 29, 2017; Big Sur Land Use Advisory Committee approved the project design and to move forward to Planning Commission (Date To Be Determined)
  • September 15, 2017; Construction Bids Due
  • Fall 2017; Site preparation work prior to culvert replacement
  • Spring 2018; Construction expected to begin

 
Installation of Security Gate

The County has installed a security gate limiting access above the “Hoist” on August 24, 2017.  This gate was installed in the location where temporary barricades have been placed.  Vehicle access beyond the gate will be limited to residents and emergency personnel. The gate may remain in place permanently to allow for temporary closures as needed, and will only be opened when road conditions above the Hoist are safe for vehicles.

 

Major Storm Repairs from “Hoist to Botcher’s Gap” (Milepost 4.0 to 7.5)

The County plans to reconstruct this 3.5-mile section of Palo Colorado Road. Numerous culverts were severely damaged, as well as several slip-outs developed from the 2017 winter storms and the Soberanes Fire. The County is working to get a Design Consultant under contract by November 2017 for the environmental and preliminary engineering. Repairs required for this project is expected to take 1-3 years to complete (2020), including design.

 

Communication

The County has designated a single point of contact for this project to receive questions and coordinate with agencies to provide a collective response:

Monterey County Resource Management Agency, Public Works Division
Contact: Christine Poe, Management Analyst II
1441 Schilling Place, South 2nd Floor
Salinas, CA  93901
(831) 755-5025

All calls and emails will be responded to as soon as possible. We will monitor conditions throughout the rain season and provide advanced notice of any actions via Chief Cheryl Goetz as well as the County’s website and social media.

 

Palo Colorado Gate

New Security Gate installed at the Hoist