County of Monterey Home Page
                   
 

 

 

Harper Canyon (Encina Hills) Subdivision EIR
(Page is currently being updated)

Project Name: Harper Canyon (Encina Hills) Subdivision EIR
File number (s): PLN000696
Location:
(Vicinity Map:)
North of San Benancio Road, East of Highway 68, Salinas
Assessor's Parcel Number (s): 416-611-001-000 and 416-611-002-000
Planning Area: Toro Area Plan
Planner(s):

Laura Lawrence, R.E.H.S., Planning Services Manager (831) 755-5148

Current Status:

Complete

Environmental Status: Draft EIR and Recirculated Draft EIR completed
Project Description:

Combined Development Permit consisting of: 1) a Standard Subdivision Vesting Tentative Map for the subdivision of 344 acres into 17 residential lots ranging in size from 5.13 acres to 23.42 acres on 164 acres with one 180-acre remainder parcel; 2) Use Permit for the removal of approximately 79 coast live oak trees over six inches in diameter for road and driveway construction; 3) Use Permit for development on slopes in excess of 30 percent; 4) Use Permit for the creation of a public water system; 5) grading for net cut and fill of approximately 2,000 cubic yards; and Design Approval.  The project is located north of San Benancio Road approximately 0.8 miles east of Highway 68, Salinas (Assessor's Parcel Numbers 416-611-001-000, 416-611-002-000, 416-621-001-000), Toro Area Plan.

Key Dates:

 

  • Fall 2010:  Project tabled due to PUC complaint against Cal-Am

  • June 15, 2010:  Release of first Final EIR; FEIR was not certified because of PUC complaint that was filed against Cal-AM

  • February 1, 2010:  45 day review period ends

  • December 2009:  Recirculated DEIR (Transportation Circulation only ) released for public review

  • December 5, 2008:  DEIR review period ends

  • October 2008: DEIR released for public review

  • June 28, 2005:  Planning Commission decision appealed to the Board of Supervisors; project remanded back to the Planning Commission for preparation of an EIR

  • January 12, 2005:  Planning Commission considered project; directed staff to proceed with preparing an EIR

  • July 24, 2003 to August 22, 2003: circulated Initial Study/MND

  • November 22, 2002: Project deemed complete

  • January 23, 2000: Application

Reports/Documents:

Related Links:
(These links are provided for information only.  The County of Monterey does not endorse any of the information found on these sites)

 

 

 

 

 

2008 Monterey County RMA Agency. All rights reserved.
Questions or Comments? Planning Department Webmaster
Disclaimer